The Senate has approved a N100.5 billion Promissory Note Programme to reimburse the Yobe State Government for constructing the Muhammadu Buhari International Cargo Airport, Damaturu.
The approval on Tuesday followed the presentation and consideration of a report by the Senate Committee on Local and Foreign Debts, chaired by Senator Aliyu Wamakko (Sokoto North).
The committee was asked by the Senate to verify the project cost at N100,509,017,234.55.
In his presentation, Wamakko explained that the request was referred to the committee on October 13, following President Bola Tinubu’s request for Senate approval.
He said Yobe constructed the airport to address insecurity challenges, improve air connectivity in the North-East and facilitate the evacuation of agricultural produce.
According to him, the project is also intended to support humanitarian operations and stimulate economic activities across Yobe and neighbouring states.
Wamakko said the airport features a 3.6-kilometre runway equipped with Category II Instrument Landing System, alongside taxiways and other essential aviation infrastructure.
He added that the facility has an apron capable of accommodating four Boeing 747 aircraft, a terminal building and a cargo shed.
According to him, other facilities include an air traffic control tower, fire station, perimeter fencing, navigational aids and aeronautical ground lighting.
Wamakko noted that the Yobe Government formally requested Federal Government takeover of the airport in a letter dated March 12, 2024, explaining that the request was consistent with aviation policies governing ownership and operation of international airports across the country.
He said the Federal Executive Council approved the takeover on August 21, subject to verification of project costs and reimbursement, which would be facilitated through a Promissory Note Programme after relevant government agencies completed verification and due-process assessments.
The committee confirmed that the N100.5 billion project cost underwent technical audit by the Federal Ministry of Aviation, while the Bureau of Public Procurement conducted a due-process review and issued a Certificate of No Objection on February 25, and the Nigerian Civil Aviation Authority confirmed that the runway, safety facilities and navigational aids complied with international aviation standards, with the airport completed, operational and test flights already conducted ahead of formal Federal Government takeover, giving the necessary legislative backing for the reimbursement of the Yobe State Government through the Promissory Note Programme.